Sample page
The Montgomery County plant as of January 21, 2020, with its dated marks.
Public-record sample, as of January 21, 2020
This is a public-record sample, not a Sustainable Gaps engagement. It shows the Montgomery County plant as of January 21, 2020, the day its EPC contractor said it was filing Chapter 11. The sample asks what a trade subcontractor, supplier or surety decides: keep committing crews and materials, or first ask for an owner assurance, joint checks or the bond position.
The Montgomery County plant as of January 21, 2020, with its dated marks.
The plant's EPC contractor announced on January 21, 2020 that it would start a Chapter 11 case that day.
The Montgomery County plant is a gas combined cycle plant.
On record by January 21, 2020: state approval with generation cost recovery capped on July 28, 2017, notice to proceed announced by the contractor on September 26, 2018, groundbreaking announced by the owner on February 15, 2019, and owner bonds in September 2019, with other funds, to finance construction and for general corporate purposes. Stated, not yet on record: a pipeline lateral in service by July 1, 2020. The date the job rested on: commercial operation estimated by mid-2021, last said by the owner in February 2019.
Each mark on the sample is either on record by the as-of day, only stated, or the date the job rested on.
A trade subcontractor, supplier or surety decides: A, keep committing crews and materials under it, or B, first ask for an owner assurance, joint checks or the bond position.
Tell us the job, the dates it depends on and when you have to decide.